Determine if fixed - date constraints are necessary
确定 固定日期 *是否必要
Nfd no fixed date
无 固定日期
But applying unnecessary fixed - date constraints can prevent microsoft project from calculating a schele properly
但是, 固定日期 *的滥用将妨碍microsoftproject正确地计算日程。
You should check all tasks with fixed - date constraints to make sure each constraint is necessary and has n ' t been appped by mistake
请检查所有带 固定日期 *的任务,确保每个*都是必要的且绝对正确。
You can also inadvertently apply fixed - date constraints by dragging the pointer on the gantt chart to create a task bar ( and thus a task )
在“甘特图”上拖动鼠标来创建任务条形图(也即是任务)时,也可能无意中应用 固定日期 *。
Because tasks with flexible constraints such as as soon as possible and as late as possible have no fixed dates to honor , they behave the same way regardless of the option you choose
因为包含弹性*(譬如“越早越好”和“越晚越好” )的任务没有 固定日期 要服从,它们将不受指定选项的影响。
Sometimes , project managers apply a fixed - date constraint when they do n ' t intend to ( for instance , if they enter a specific start date and finish date for a task after they enter the task )
有时项目经理会无意应用了 固定日期 *(譬如在输入了任务之后,又输入确定的开始日期和结束日期) 。
When a task really must start or finish on or near a specific date , you can apply the appropriate fixed - date constraint for that task , such as the must start on constraint or the must finish on constraint
如果任务必须在(或接近)某个指定日期开始或完成,可以对该任务应用 固定日期 *,如“必须开始于”*或“必须完成于”*。
Once these tasks are pnked , microsoft project will always schele the start date for hanging clocks relative to the finish date for painting walls , no matter when these tasks occur
这些任务相互链接后,无论它们何时发生, microsoftproject总会根据“粉刷墻壁”任务的完成日期来排定“悬挂钟表”任务的开始日期,从而避免将任务*在某个可能无法实现的 固定日期 。