本人现供职于一家建筑工程公司,接了一个单子,但是有一篇建筑要求需翻译...
发布网友
发布时间:2024-09-27 11:02
我来回答
共1个回答
热心网友
时间:2024-09-28 03:27
6.8.1 coating projects
1, the material requirements
Be bored with child and coating should have factory proof and environmental quality examination.
2, operation conditions
(1) the basic dry, moisture content is not more than 8%,
(2) door window glass installation ends, wet homework finished, pipeline construction of ground pressure finished,
(3) before construction well between example and checked eligibility,
(4) and door window frame, condole with the handover parts paste textured paper tape completes the finished product protection.
3, technological process
Basic level processing - embedded, batch putty - play in the first time sand paper - scraping the 2nd times be bored with child - playing the second time sand paper - the first time paint brush furnace-rough play sand paper - brush the 2nd times paint - play sand paper - brush paint a third time
4, key points of construction
(1) the basic processing
Will grassroots dust and ash, smeary clean. With white cement (or big white powder), talcum powder with 108 plastic adjustable putty, fill the uneven surface flat grassroots Pang, dry after appearing sanded grinding smooth, then full blow be bored with child, after being dry with a 1) sandpaper level off, and remove float ash.
(2) besmear brushs the first time coatings
First the ceiling carefully cleaned, cloth will dust rub-up. Besmear brushs order from left to right. By using the new PaiBi besmear brush, PaiBi, pay attention to the activities of the pen MaoLi off. Coating should mix before use, according to the grassroots and environmental temperature condition, can add 10% water dilute, in case the head again coating shi besmear not open. Dry after filling putty, stay after filling putty dry after appearing, with 1 sand paper burnish, and sweep clean.
(3) besmear brushs the 2nd times coatings
Operation requirements with the first go paint, coating before fully mixing, such as not very thick, unfavorable water or water less as far as possible, in case the show. Film after drying, with fine sand the surface little a knot in one's heart and PaiBi MAO burnish drops, after polishing cloth clean.
(4) besmear brushs a third time coatings
Operation requirements with the 2nd times coatings. Due to quick drying, continuous film should be quick operation, besmear brushs from left side when beginning, gradually to the other side, besmear after a row must pay attention immediately before a PaiBi, avoid joint obvious but again separately processing.
5, quality standards
(1) used coating varieties, model and performance should comply with the design requirements. Inspection method: check product certificate, performance test report and approach acceptance record.
(2) finishing engineering of color, design should comply with the design requirements. Inspection method: observation.
(3) finishing works should be finishing evenly, bond and firm, not leak painting, through at the end, peeling and off powder. Observations; inspection method: Hand touch inspection.
(4) finishing engineering of basic level processing should meet the following requirements. Observations; inspection method: Hand touch check; Check construction records.
1) concrete or plasterer layer grassroots in finishing before coating should besmear brushs alkali closed primer.
2) concrete or solvent-based coating plastering grassroots besmear, moisture content must not be more than 8%, Besmear brushs emulsion coatings, moisture content must not be more than 10%. The moisture content of timber grassroots must not be more than 12 per cent.
3) the basic putty should level off, solid, durable, no pulverization, peeling and crack, Interior wall be bored with child, the bond strength shall conform to the relevant provisions.
6, product protection
(1) before construction shall not cover the doors and Windows and metope shade; protect
(2) be bored with child and coatings when construction, construction site with ground requirements changes timely striped cloth or laying plastic, prevent pollution ground;
(3) after completion timely with board will protect mouth, horn, prevent collisions damage;
(4) tear open shelves when presenting touch loss metope coatings;
(5) painter construction are prohibited during the stamped on the construction site, and already finished prevent tank knocked off, coating pollution metope.
The ninth festival scaffold project
6.9.1 scaffold selection
According to this project, the structure and features, decorate metope of using four walk type the hydraulic lift platform joint working to complete &interior wall painting and glass curtain wall installation work. Wall lining and paint the work using tools type scaffold completed.
Chapter 7 engineering key part construction plan and the measures
Section 1 of tower foundation construction
The main tower choose arm length 50 meters TC5013B flat arm tower crane as vertical transport hoisting equipment.
Crane foundation foundation slab, crane is located feet column (or embed standard festival) pouring in foundation slab of one-time consumption, in order to ensure the structure was not affected crane dismantled will only basic upper embedded column footing (or standard festival) removal.
Crane beam slab based elevation, thickness, concrete strength grade anti-permeability level with the proposed construction project foundation slab concrete. Crane beam slab foundation construction, so as to first crane installation and use, simultaneously must make base of rebar connection, concrete juncture measures.
The second quarter special overhung structure construction
This project layer 3 a partial overhung structure, the conventional mode branch shall not apply to the project.
1 a: local and scheme of the span.a height reach 8 meters bowl buckle tubular steel scaffolding as templates support. This support four steps frame, each step is about 2 meters, support scaffolds must with each layer of solid structure connections, prevent inclination deformation.
Problems added:
Partly shown below:
2, the scheme ii: on the second floor structure on the span.a slanting brace, supported by dense steel composition, steel pipe in central and fixed channels connected, bottom fixed in a floor space of reinforced ring buckle embed in connection with the bowl of upper level, pipe to buckle form stable formwork supporting system
本人现供职于一家建筑工程公司,接了一个单子,但是有一篇建筑要求需翻译...
This project layer 3 a partial overhung structure, the conventional mode branch shall not apply to the project.1 a: local and scheme of the span.a height reach 8 meters bowl buckle tubular steel scaffolding as templates support. This support four steps frame, each step is about ...
古文翻译
28庞恭要陪太子到赵国去做人质,庞恭对魏王说:“现在,如果有一个人说街市上有老虎,您相信吗”“魏王说:“不相信。”庞恭说:“如果是两个人说呢?”魏王说:“那我就要疑惑了。”庞恭又说:“如果增加到三个人呢,大王相信吗?”魏王说:“我相信了。”庞恭说:“街市上不会有老虎那是很清楚的,但是三个人说...
明天面试,要求英文的自我介绍,大家帮个忙翻译一下吧,谢谢啦。
接下来由这部份个人基本情况,自然地过渡到一两个自己本科或工作期间圆满完成的事件,以这一两个例子来形象地、明晰他说明自己的经验与能力,例如:在学校担任学生干部时成功组织的活动;或者如何投入到社会实践中,利用自己的专长为社会公众服务;或者自己在专业上取得的重要成绩以及出色的学术成就。接下来要着重结合你的职业...
...去了好几家单位面试,都要求提供英文简历,本人水平有限谢
Male | Married | 1984 年 10 month old | Account: Jiangsu Suzhou | now living in Suzhou, Jiangsu | 5 years experience | Party | ID: ***|***( phone) | E-mail:Self-evaluation College to become Communist Party members, cooperation and strong .4 years of quality experience in...
我想问一下日本公司的职位问题,什么事系长,课长,之类的?知道请详细解释...
日本公司一般管理体制为: 社长:相当于国内的董事长,掌有公司内最多股份,决定公司一切事物。 部长:掌管一个方面的事物。 课长:相当于国内的科长,小范围内的管理。 主任:一个办公室内的管理。 扩展资料: (一)最高层 取缔役会:董事会 会长(会长):是等同于我们所说的董事长,当然这个称呼的日本说法还有一个是...
招聘会上的个人简历和个人形象应该注意哪几点...
还有的求职信这样写:“本人于6月5日要放假回家,敬请人事经理务必于6月1日前复信为盼。”表面上看,好像很客气,却在限定时间,给对方下命令,容易让人不快。②自以为是、带有要挟意味。比如:“现已有多家公司要聘我,所以请贵公司从速答复”。这实际上是在威胁人家,好像在说:“我可是一位...
谁能帮我找一篇高中作文,辞藻华丽,例证较多的,话题是残缺也是一种美
就像一位书法家看到敦煌残纸,它会想像出一笔一画的动势,普通人则只当是残字而已;一个不了解中国文化审美的人看到圆明园,他只能看到一堆瓦砾,美从何来?而熟悉中国文化审美的人看时则可填补出所缺的东西,了解这一段惨痛历史的有爱国心的中国人看圆明园,当又是另一种心情。这不知算不逄残缺...
在人际关系中要怎么说话??
另一个重要的开场白(也是立竿见影的)是征求建议。例如,您可以问一个热心的园艺家:"我想把花园中的一年生植物改种多年生的,您建议种什么好呢?" 或对于一个在家或办公室办公的人,您可以问:"我想买一部传真机。您有什么好的推荐吗?"如果没有反应,可以问他的观点。问他或她有关任何方面的观点是很稳妥的:政治...